Direct Cost Charging Policy on Sponsored Projects

Purpose

The purpose of this policy is to ensure that Hope College Principal Investigators
comply with the Federal Office of Management and Budget (OMB) standards
regarding direct costs on sponsored projects. Direct costs on sponsored projects must be allowable, allocable, and reasonable. OMB provides the standards to which must conform in Circular A-21, Cost Principles for Educational Institutions (http://www.whitehouse.gov/omb/circulars/a021/a021.html) and A-110, Uniform Administrative Requirement for Grants and Agreements with Institutions of Higher Education (http://www.whitehouse.gov/omb/circulars/a110/a110.html).

Definitions

Direct costs are costs associated with a specific sponsored project that can be
directly assigned to essential activities with relative ease and a high degree of
accuracy. They include such costs as personnel (salaries and fringe benefits),
supplies, equipment, travel, and other expenses necessary to the conduct of
sponsored activities (Circular A-21: Section D1).

Sponsored activities are those externally funded activities that must be separately budgeted and accounted for according to the terms of the sponsoring organization, State regulatory precepts, and policy. Sponsored projects may include grants, contracts, and cooperative agreements with any Federal Agency, State Agency, or non-Governmental Organization that supports research, training and public service activities.

Facilities and administrative (F&A) costs, for the purpose of this policy, are
defined as costs that are incurred for common or joint objectives and, therefore, cannot be identified readily and specifically with a particular sponsored project, an instructional activity, or any other institutional activity. F&A costs are synonymous with "indirect" costs, as outlined in OMB Circular A-21.

Determining Factors

In making payments for activities funded by grants, contracts, and cooperative
agreements, the university department/unit administering the project must
determine whether the costs are allowable, allocable, and reasonable.

Allowable Costs

To be allowable a cost must be authorized for payment under the terms of the
award made by the sponsor (Circular A-21: Section C2). The question to ask
is, “Will the sponsor pay for this expense?” The tests as to whether a cost is
allowable are:

  1. the cost must be reasonable;
  2. it must be possible to allocate the cost to a sponsored project using the
    principles and methods provided by the federal or state regulations;
  3. the cost must be given consistent treatment by application of generally
    accepted accounting principles appropriate to the circumstances and in
    compliance with Hope College’s Disclosure Statement; and,
  4. the cost must conform to any limitations or exclusions set forth in Circular A-21, the award document, the sponsoring agency's guidelines in terms of types or amounts of cost items, State regulations, or policy.

Allocable Costs

A cost is allocable if a specific good or service is chargeable or assignable to
a particular cost objective (i.e., a specific function, project, sponsored project,
department or the like) in accordance with the relative benefits received or other equitable relationship (Circular A-21: Section C4). The question to ask is, “Is the expense related to the project?” The tests as to whether a cost is allocable are:

  1. is the cost incurred solely to advance the work of the sponsored project;
  2. does the cost benefit both the sponsored project and other work of
    the institution in proportions that can be approximated through use of
    reasonable methods; or,
  3. is the cost necessary to the overall operation of the institution based on
    the principles in Circular A-21 or as deemed assignable by the sponsored
    project.

    Note: In the case of equipment or other capital items purchased with specific authority of a sponsored award, the amount authorized for such purchases is assignable to the sponsored project regardless of the use that may subsequently be made of the items. Any cost allocable to a particular sponsored project according to the standards of the project may not be shifted to other sponsored projects to compensate for overruns, other reasons of convenience, or to avoid restrictions in law or the terms of the sponsored award. Neither may costs allocable to activities sponsored by industry, foreign governments, or other sponsors be shifted to federally-sponsored projects.

 

Reasonable Costs

A cost is considered reasonable if the nature and amount of the goods or
services acquired for or applied to a specific sponsored project reflect the actions of a prudent person under the circumstances prevailing when the decision to incur the cost was made (Circular A-21: Section C3). The question to ask is, "Is the expense reasonable?" Major considerations in determining the
reasonableness of a cost are:

  1. whether or not the cost is generally recognized as necessary for the
    performance of the sponsored project or the operation of the institution;
  2. the restraints or requirements imposed by factors such as arm's-length
    bargaining, Federal and State regulations, terms and conditions of a
    sponsored agreement, or agency guidelines;
  3. whether or not the individuals acted with prudence in considering their
    responsibilities to the institution, its employees, its students, State or
    Federal Government, and the public at large; and,
  4. whether or not the actions taken to incur the cost are consistent with
    established institutional policies and practices applicable to the work of the institution generally and inclusive of sponsored projects.

Determination Strategy

The first question to ask in making a determination as to whether a particular cost on a sponsored project is allowable, allocable, and reasonable is: Does the cost benefit the project? While a prudent person might have proposed a certain cost that is no longer necessary at the point a project is funded, rebudgeting must ensure continued benefit to the project in question rather than benefit a different project or purpose. Several documents can be reviewed to help determine whether a particular cost is allowable, allocable, and reasonable. While the following list is not exhaustive, it does provide a reasonable course of action that for many circumstances will provide a measure of confidence as to the allowable, allocable, and reasonable nature of individual costs.

Approved Project Budget
The first document to review is the agency-approved budget for the project. Does the proposed expense appear as a line item in the budget? If the item does not appear in the budget, the item may be allowable under rebudgeting authority or with prior approval in writing from the funding agency.

Award Document or Contract
The allowability of certain costs may be addressed in the award document or the contract issued by the sponsoring agency. In some instances, grant awards may identify certain costs based on recommendations from the peer review system that are specifically not allowed by the sponsoring agency.

Agency Guidelines
Most agencies have guidelines for administering awards that give direction on allowing certain costs. Travel costs may appear in the budget, for example, yet the specific cost of airfare to attend a meeting in Europe may require prior approval according to the guidelines of the sponsoring agency.

OMB Circulars A-21 and A-110
The primary regulations governing the determination of whether costs are
allowable, allocable, and reasonable on federal grants, contracts, and
cooperative agreements are OMB Circulars A-21 and A-110. They also serve as the guidelines followed by in making similar determinations on all externally sponsored projects. Section J of Circular A-21 identifies allowable costs and gives guidance on how such costs are to be charged directly to a sponsored project or allocated as facilities and administrative (F & A) costs. The institutionis expected to be consistent in its treatment of expenses, but Circular A-21 also provides guidelines for determining when an exception can be made. While “like” circumstances must be treated the same, there is a degree of latitude with “unlike” circumstances.

Cross References

There are additional policies relevant to the charging of direct costs Hope
Colleges Grant Administration website as well as the Direct Charging Procedures
on Sponsored Projects for implementing this policy.